Keystone Energy's four-project portfolio totals 850 TPD across different delivery stages: one fully commissioned plant, two plants in commissioning and one completed pilot.

Project Portfolio

Swipe the table sideways to see client, location and status.

Keystone Energy torrefaction project portfolio and verified delivery status
CapacityInputOutputClientLocationStatus
500 TPDMunicipal Solid WasteTorrefied MSWNTPC Ltd. (via NVVN)Gorakhpur, Uttar PradeshCommissioning
200 TPDRice straw biomassTorrefied BiomassTransPacific EngineersSangrur, PunjabCommissioning
100 TPDLegacy waste, RDF and biomassTorrefied CharcoalKeystone GreentechWarangal, TelanganaFully commissioned
50 TPDSTP sludgeTorrefied CharcoalDelhi Jal BoardDelhiPilot completed
Existing Keystone Energy photograph associated with the 500 TPD Gorakhpur MSW torrefaction project
Gorakhpur, Uttar Pradesh — 500 TPD MSWExisting Keystone project photograph. Client: NTPC Ltd. via NVVN. Verified status: commissioning.
Existing Keystone Energy photograph from its Punjab and Haryana biomass project portfolio
Sangrur, Punjab — 200 TPD rice straw biomassClient: TransPacific Engineers. Verified status: commissioning. The adjacent image is from Keystone’s Punjab/Haryana biomass portfolio; its exact site mapping remains unconfirmed.
Existing Keystone Energy photograph associated with the fully commissioned 100 TPD Warangal torrefaction plant
Warangal, Telangana — 100 TPD legacy waste, RDF and biomassExisting Keystone project photograph. Client: Keystone Greentech. Verified status: fully commissioned.
Existing Keystone Energy photograph associated with the completed 50 TPD Delhi Jal Board STP sludge pilot
Delhi — 50 TPD STP sludge pilotExisting Keystone project photograph. Client: Delhi Jal Board. Verified status: pilot completed.

Engineering Edge

Keystone Energy's proprietary continuous torrefaction technology is engineered for 6,000+ operating hours per year in modular 50–1000 TPD plant configurations and is compatible with multiple feedstocks such as municipal solid waste, RDF, biomass and STP sludge.

The process produces dry, carbon-dense solid fuels known as Torrefied MSW, Torrefied Biomass, Torrefied Charcoal, BioChar and Green Coal. Measured calorific ranges are feedstock-specific: 3,700–4,000 Kcal/kg for MSW, 4,000–4,300 for rice straw, 3,800–4,000 for RDF, 3,500–3,800 for undigested STP sludge and 3,700–6,000 for woody biomass. These fuels are designed for coal-replacement and co-firing applications in thermal power plants, cement plants, steel plants and industrial boilers.